Coastal highway turns inland: Tinubu’s flagship road will leave the sea at Ondo and join the East-West Road
Umahi calls it a wonderful engineering decision by the President. Ilaje and Itsekiri leaders call it a betrayal, and Donald Duke’s warning that Nigeria could not afford a coastal road now looks partly vindicated.
By The Atlantic Digest · Abuja
Abuja — The Lagos–Calabar Coastal Highway, the most expensive and most argued-over infrastructure project of President Bola Tinubu’s administration, will no longer follow the coast for much of its length. Works Minister David Umahi has confirmed that, beyond Lagos and Ogun, the road will leave the shoreline. It will instead turn inland through Ondo to the Edo border, then continue along the existing East-West Road rather than a new coastal alignment through the Niger Delta. Umahi described the change as a wonderful engineering decision by the President.
Defending the decision, Umahi said the original route through Ondo ran across terrain with pits more than 100 metres deep and no suitable sand nearby, which would have driven costs sharply higher. He said the government had no regrets about the decisions taken in Ondo. The diverted sections, known as 4A and 4B, cover about 67 kilometres, roughly 27 in Ogun and 40 in Ondo, and filling of more than ten metres there is said to be nearly complete. From the Ondo–Edo axis, he said, Mr Tinubu had directed that the highway follow the existing East-West corridor rather than cut a new path. A 104-kilometre Ondo–Edo stretch, including a 45-kilometre bypass around Benin City, will carry traffic around the city’s congested centre.
Beyond Edo, the minister described a 129-kilometre dual carriageway from Edo through Delta to the Bayelsa border, with work expected to begin in November. He said some sections of the existing road would have to be raised by about two metres to stay above flood levels. At the eastern end, the 65 kilometres of Sections 3A and 3B in Cross River and Akwa Ibom are said to be more than 30 per cent complete, with an 82-kilometre Section 5 in Akwa Ibom still ahead. In Lagos, the first 47.47-kilometre section from Victoria Island is ready for commissioning, and the 55-kilometre second section is due to receive its dual pavement next month.
Strictly, the change does not remove Ondo from the project. The road will still pass through the state for about 40 kilometres. What it removes is Ondo’s coastline. The original concept was a single shoreline route through Ilaje country in Ondo and Itsekiri communities in Delta. That is now being abandoned in favour of an inland route joined to a road that has existed for decades. For a project sold to Nigerians as a transformational coastal corridor, that is a fundamental change.
The communities who expected the road on their coast are not persuaded by the engineering case. At a joint meeting in Lagos last month, Ilaje and Itsekiri leaders resolved to fight for the original alignment and threatened legal action. They described the minister’s explanation as a blatant falsehood. Their own figures turn his cost argument around. They estimate construction along the coast at between ₦4 billion and ₦7.5 billion per kilometre, against ₦7.5 billion to ₦12 billion for the inland route. They also say the stretch from Olosunmeta to the Itsekiri axis would be 100 to 110 kilometres on the coast but 170 to 190 kilometres inland. Those are the communities’ figures and have not been independently verified, but they go to the heart of the dispute. Ondo coastal communities have since asked the federal government to investigate the change.
The political sting comes from a prediction made two months ago. On 4 August, appearing on Arise Television’s Prime Time, Donald Duke, the former Cross River governor and now the presidential candidate of the Peoples Redemption Party, said the road would not go beyond Epe. Epe is the eastern edge of Lagos, close to the Ogun border. He said the country could not afford it and that the swampy Bayelsa coastline would need far too many bridges. He argued the money would be better spent on fixing the existing Lagos–Calabar road and on electricity and healthcare.
The Presidency replied within a day. Tope Ajayi, Senior Special Assistant to the President on Media and Publicity, said Duke was arguing against reality. He said the project had already reached Ogun State and that work was under way on the Ondo and Akwa Ibom sections. On the narrow point, the Presidency was right: construction has gone beyond Epe, and the road is being built in Ogun and Ondo.
On the larger point, Umahi’s announcement goes a long way towards Duke’s view. The former governor’s argument was that a continuous coastal highway across the Niger Delta was unaffordable and impractical. The government has now effectively conceded that, at least for the stretch from Ondo to the Delta. It cites cost and terrain to justify falling back on the East-West Road, a route Nigerians already know, and one whose own long-delayed reconstruction has been a story of its own. Duke’s Epe claim was wrong in detail. His central warning about cost and the coastal concept is substantially borne out by the government’s own decision.
Cost has shadowed the project from the beginning. The first 47.47-kilometre section was awarded to Hitech Construction, a company linked to the Chagoury group, for ₦1.067 trillion, roughly ₦22.5 billion per kilometre on our arithmetic. A $747 million syndicated loan led by Deutsche Bank was arranged to finance it. Critics, including former Vice President Atiku Abubakar, have repeatedly demanded a full public account of the total cost and of how the contract was awarded. The government has defended the project as an economic corridor that will open up the south-west and the coast to investment, tourism and trade.
The rerouting gives both sides new material. For the government, choosing the East-West Road is a cost-saving correction that will connect the corridor sooner and more cheaply. For its critics, it raises an obvious question. If a coastal road beyond Ondo was always going to be too difficult and too expensive, why was the project announced, financed and promoted as a continuous coastal highway in the first place? They also ask what the trillions committed so far will buy if the coastline is ultimately left behind.
For the people of the Ilaje and Itsekiri coastline, the question is more immediate. Their communities, among the most isolated in the south, were promised a road that would end their dependence on boats and open their waterfronts to trade. The new route leaves them where they were. They have promised to lobby, mobilise traditional rulers and go to court if necessary. With the 2027 elections approaching and the President’s own candidates seeking votes in Ondo and Delta, it is unlikely to be the last word on the route.