The Atlantic Digest
Nigeria desk · Saturday, 10 October 2026
NIGERIA · CROSS RIVER · POWER
‘Ekong Etta is crying for light’: Cross River community in darkness for 10 months appeals to Governor Otu
A broken transformer has left the community without electricity since about the start of the year. Residents say appeals to the electricity company have gone nowhere, and are now asking the state government for a new 500KVA transformer. Their plight mirrors a pattern of long blackouts in communities around Calabar.
The Atlantic Digest | Calabar
For almost a year, the community of Ekong Etta in Cross River State has lived without public electricity. Its transformer has broken down, and residents say repeated appeals to the electricity authorities have produced no result. They have now turned to Governor Bassey Edet Otu for help.
“Our community has been without electricity for about 10 months and is gradually approaching one full year,” said Engineer Johnsmith Okpo, chairman of the Ekong Etta Community Transformer Committee, in an appeal reported by The Beagle News on Friday. “Your Excellency, Ekong Etta is crying for light. Please hear our cry.”
What went wrong
According to the committee, the community’s existing transformer has become seriously defective and can no longer supply power. The committee says it has made several efforts to resolve the problem and followed up repeatedly with the relevant electricity authorities, but the transformer has been neither repaired nor replaced.
The committee is asking the state government to provide a new 500KVA transformer. It says the community is ready to work with the state government, the Port Harcourt Electricity Distribution Company (PHED), which supplies electricity in Cross River, and other agencies on its installation, protection and maintenance. The offer to protect the equipment is significant: theft and vandalism of transformers and cables are a common reason why distribution companies are reluctant to install new equipment in some communities.
The appeal did not say which local government area Ekong Etta is in, how many people live there, or exactly when the transformer failed. Neither PHED nor the Cross River State Government had publicly responded by Saturday.
Life without light
The committee says the blackout has disrupted household routines and economic activity. Small business owners and artisans who rely on electricity for their equipment and services have been especially hard hit. In communities in this situation, those who can afford it run generators, at a time when petrol costs more than N1,300 a litre; those who cannot have to cut their hours or close.
Students have struggled to study, especially at night, the committee said. Elsewhere in Calabar, residents in similar blackouts have described paying to charge their phones at generator-powered charging centres and managing without refrigeration in a hot, humid climate. Ten months without power is long enough for its effects to show in incomes, school results and health.
Not the only community in the dark
Ekong Etta’s complaint is part of a pattern in and around Calabar. In January, residents of Ikpai Ohom and Big Qua Town in Calabar Municipality said they had been without power for about six months after their transformer, installed in 1968, was removed for repairs in August 2025 and never returned, although they had contributed money towards the work. “It is deeply disheartening to say that we have had electricity for fewer than five months in 2025,” one resident, Victoria Omini, told The Guardian. They too appealed to Governor Otu after saying PHED did not respond.
In 2024, the Nyangassang community near Calabar’s Margaret Ekpo International Airport said PHED had disconnected its overloaded transformer, which had a burnt neutral, leaving thousands of households without power. Residents alleged that the company acted because they could not pay for repairs themselves.
The cases follow a familiar pattern. Ageing transformers fail, the distribution company is slow or unwilling to replace them, and communities are asked to raise money for repairs themselves. When that fails, they turn to the state government or their lawmakers. The Nigerian Electricity Regulatory Commission has repeatedly told distribution companies not to force communities to buy or repair transformers, and its rules say customers who fund such equipment must be repaid. In practice, communities are still often asked to pay.
Who is responsible
Responsibility for local power supply is shared. PHED owns and operates the distribution network in Cross River, Rivers, Akwa Ibom and Bayelsa, and is responsible for maintaining transformers and supply to its customers. Under the Electricity Act 2023, states can also regulate electricity markets within their borders and invest in generation and distribution, and several state governments have bought and installed transformers for communities. Governor Otu’s administration has said it is willing to act on electricity problems and has previously ordered an assessment of electrification needs across the state.
A 500KVA transformer is a significant investment: with installation and connection, it typically costs tens of millions of naira. But it is small compared with the economic losses of a community left without power for nearly a year.
What comes next
The Ekong Etta committee has framed its request as a partnership, offering to protect and help maintain any new transformer. Whether the state government or PHED responds, and how quickly, will be watched by other communities in the state with the same problem. The appeal also comes in an election season, with governorship elections due in February 2027, when residents’ demands for basic services carry particular weight.
For now, residents of Ekong Etta are entering an 11th month without power.
Editor’s note: This report is based on the appeal by the Ekong Etta Community Transformer Committee as reported by The Beagle News on 9 October 2026, and on earlier reporting by The Guardian, Leadership and Nigerian Tribune on blackouts in other Calabar communities. The Atlantic Digest was unable to confirm the community’s local government area or population, or to obtain responses from PHED or the Cross River State Government, by the time of publication. Descriptions of the blackout’s effects on businesses and households reflect the committee’s account and common conditions in affected communities.